[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51864":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51864,53,1,"单选题","下列工程进度控制的措施中，属于进度控制合同措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制进度计划和进度控制工作流程",false,{"key":16,"text":17,"correct":14},"B","建立工期超前或延误的奖惩制度",{"key":19,"text":20,"correct":21},"C","选用适当的工程发承包模式",true,{"key":23,"text":24,"correct":14},"D","分析比较实际进度与计划进度","进度控制措施有组织措施、技术措施、经济措施、合同措施和信息管理措施。进度控制的合同措施主要包括：选择合理的合同结构、加强合同管理、严格控制合同变更、协调合同工期与进度计划之间的关系；采用适当的工程发承包模式，如采用DB\u002FEPC总承包模式等，可有效减少合同界面；采用CM模式，对工程实行分段设计、分段发包、分段施工，以缩短建设工期；加强工程风险管理与索赔管理等。A项属于组织措施；B项属于经济措施；C项属于合同措施；D项属于信息管理措施。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]