[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51863":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},51863,53,1,"单选题","工人必需消耗的工作时间包括有效工作时间、不可避免的中断时间和（ ）时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","休息",true,{"key":16,"text":17,"correct":18},"B","多余",false,{"key":20,"text":21,"correct":18},"C","偶然",{"key":23,"text":24,"correct":18},"D","停工","必需消耗的时间是指工人在正常施工条件下，为完成一定产品（工作任务）所消耗的时间。必需消耗的时间是编制劳动定额的主要根据，包括：①有效工作时间；②休息时间；③不可避免的中断时间。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]