[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51861":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51861,53,1,"单选题","工人工作时间中的休息时间属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","停工时间",false,{"key":16,"text":17,"correct":14},"B","不可避免中断时间",{"key":19,"text":20,"correct":21},"C","必需消耗的时间",true,{"key":23,"text":24,"correct":14},"D","损失时间","必需消耗的时间是指工人在正常施工条件下，为完成一定产品（工作任务）所消耗的时间。必需消耗的时间是编制劳动定额的主要根据，包括：①有效工作时间；②休息时间；③不可避免的中断时间。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]