[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51860":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},51860,53,1,"单选题","下列工人工作时间中，属于有效工作时间的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","辅助工作时间",true,{"key":16,"text":17,"correct":18},"B","休息时间",false,{"key":20,"text":21,"correct":18},"C","多余时间",{"key":23,"text":24,"correct":18},"D","偶然时间","有效工作时间是指从生产效果来看，与产品生产直接有关的时间消耗，包括：①基本工作时间；②辅助工作时间；③准备与结束工作时间。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]