[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51854":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},51854,53,1,"单选题","下列施工成本考核指标中，属于项目成本考核指标的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目施工成本降低率",true,{"key":16,"text":17,"correct":18},"B","目标总成本降低率",false,{"key":20,"text":21,"correct":18},"C","施工责任目标成本实际降低率",{"key":23,"text":24,"correct":18},"D","施工计划成本实际降低率","施工成本考核指标包括：①项目成本考核指标。包括项目施工成本降低额和项目施工成本降低率；②项目经理部可控责任成本考核指标。包括项目经理责任目标总成本降低额和降低率、施工责任目标成本实际降低额和降低率和施工计划成本实际降低额和降低率。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]