[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51844":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51844,53,1,"单选题","施工成本管理的基本流程是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","成本分析→成本核算→成本预测→成本计划→成本控制→成本考核",false,{"key":16,"text":17,"correct":14},"B","成本核算→成本预测→成本考核→成本分析→成本计划→成本控制",{"key":19,"text":20,"correct":21},"C","成本预测→成本计划→成本控制→成本核算→成本分析→成本考核",true,{"key":23,"text":24,"correct":14},"D","成本计划→成本控制→成本预测→成本核算→成本考核→成本分析","施工成本管理是一个有机联系与相互制约的系统过程，包括：①施工成本预测；②成本计划；③成本控制；④成本核算；⑤成本分析；⑥成本考核等环节。因此，施工成本管理的流程为：成本预测→成本计划→成本控制→成本核算→成本分析→成本考核。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]