[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51843,53,1,"单选题","建设工程成本管理内容中，（ ）是目标成本的一种表达形式，是建立施工项目成本管理责任制、开展成本控制和核算的基础，也是施工成本控制的主要依据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工成本分析",false,{"key":16,"text":17,"correct":18},"B","施工成本计划",true,{"key":20,"text":21,"correct":14},"C","施工成本控制",{"key":23,"text":24,"correct":14},"D","施工成本核算","施工成本计划是以货币形式表达的施工项目在计划期内的生产费用、成本水平、成本降低率，以及为降低成本所采取的主要措施和规划的具体方案。施工成本计划是目标成本的一种表达形式，是建立施工项目成本管理责任制、开展成本控制和核算的基础，也是施工成本控制的主要依据。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]