[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51839":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51839,53,1,"单选题","项目成本降低额和项目成本降低率用于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定生产消耗",false,{"key":16,"text":17,"correct":14},"B","制定工程报价",{"key":19,"text":20,"correct":21},"C","考核项目成本管理水平",true,{"key":23,"text":24,"correct":14},"D","反映企业综合收益水平","计划成本与实际成本的差额称为项目成本降低额，项目成本降低额与计划成本的比值称为项目成本降低率，这两项指标都是考核项目成本管理水平的依据。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]