[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51832":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51832,53,1,"单选题","工程的项目成本降低额和项目成本降低率（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","反映了建筑行业的综合收益水平",false,{"key":16,"text":17,"correct":14},"B","依据工程的计划成本和预算成本计算",{"key":19,"text":20,"correct":21},"C","依据工程的计划成本和实际成本计算",true,{"key":23,"text":24,"correct":14},"D","依据工程的预算成本和实际成本计算","实际成本与计划成本进行比较，可揭示成本计划的节约和超支，考核企业施工技术水平及技术组织措施的贯彻执行情况和企业经营效果。计划成本与实际成本的差额称为项目成本降低额，项目成本降低额与计划成本的比值称为项目成本降低率。这两项指标都是考核项目成本管理水平的依据，其计算公式为：项目成本降低额＝计划成本－实际成本；项目成本降低率＝项目成本降低额÷计划成本×100%。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]