[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51831":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51831,53,1,"单选题","关于工程项目计划成本的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","计划成本就是工程项目的预算成本",false,{"key":16,"text":17,"correct":14},"B","计划成本就是工程项目的制造成本",{"key":19,"text":20,"correct":21},"C","计划成本就是工程项目的目标成本",true,{"key":23,"text":24,"correct":14},"D","计划成本就是工程项目的完全成本","计划成本也称目标成本，是指施工单位在预算成本的基础上，根据计划期有关资料，在实际成本发生前期计算应达到的成本标准。计划成本是建筑企业考虑降低成本措施后的成本计划数，反映企业在计划期内应达到的成本水平，对加强建筑企业和工程项目经济核算，建立和健全施工项目成本管理责任制，控制施工过程中产生的费用，降低施工成本具有十分重要的作用。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]