[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51829":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51829,53,1,"单选题","编制招标工程量清单时，下列费用中，属于其他项目清单的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","住房公积金",false,{"key":16,"text":17,"correct":18},"B","总承包服务费",true,{"key":20,"text":21,"correct":14},"C","社会保险费",{"key":23,"text":24,"correct":14},"D","工伤保险费","其他项目清单是指分部分项工程项目清单、措施项目清单所包含的内容以外，因招标人的特殊要求而发生的与拟建工程有关的其他费用项目和相应数量的清单。其包括：①暂列金额；②暂估价；③计日工；④总承包服务费。ACD三项均属于规费项目清单。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]