[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51824":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51824,53,1,"单选题","编制招标工程量清单时，暂列金额应列入（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","暂估价",false,{"key":16,"text":17,"correct":14},"B","措施项目清单",{"key":19,"text":20,"correct":21},"C","其他项目清单",true,{"key":23,"text":24,"correct":14},"D","总承包服务费","其他项目清单应根据拟建工程的具体情况列项，包括：①暂列金额；②暂估价；③计日工；④总承包服务费。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]