[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51823":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51823,53,1,"单选题","分部分项工程量清单的项目编码由（ ）位阿拉伯数字组成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","11",{"key":19,"text":20,"correct":21},"C","12",true,{"key":23,"text":24,"correct":14},"D","13","项目编码是指分部分项工程量清单项目名称的数字标识。分部分项工程量清单的项目编码，应采用12位阿拉伯数字表示。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]