[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51822":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51822,53,1,"单选题","在发生工程变更、施工索赔、增加新的工程项目等情况时，可作为工程量调整和进行工程索赔的依据是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工定额",false,{"key":16,"text":17,"correct":14},"B","计价规范",{"key":19,"text":20,"correct":14},"C","施工规范",{"key":22,"text":23,"correct":24},"D","工程量清单",true,"工程量清单为调整工程量、进行施工索赔提供依据。工程实施过程中发生工程变更、施工索赔、增加新的工程项目等情况时，可以选用或者参照工程量清单中的分部分项工程或计价项目与合同单价来确定变更项目或索赔项目的单价和相关费用。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]