[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51819":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51819,53,1,"单选题","实行工程量清单计价应采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工料单价法",false,{"key":16,"text":17,"correct":18},"B","综合单价法",true,{"key":20,"text":21,"correct":14},"C","扩大单价法",{"key":23,"text":24,"correct":14},"D","预算单价法","实行工程量清单计价应采用综合单价法。综合单价是指完成一个规定清单项目所需的人工费、材料和工程设备费、施工机具使用费和企业管理费、利润及一定范围内的风险费用。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]