[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51809":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51809,53,1,"单选题","施工过程中工种之间交叉作业造成的不可避免的剔凿、修复、清理等用工，属于预算定额中人工工日消耗量指标中的（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","基本用工",false,{"key":16,"text":17,"correct":14},"B","超运距用工",{"key":19,"text":20,"correct":14},"C","辅助用工",{"key":22,"text":23,"correct":24},"D","人工幅度差用工",true,"人工幅度差用工是指人工定额中未包括的，而在一般正常施工情况下又不可避免的一些零星用工。其内容为：①各种专业工种之间的工序搭接及土建工程与安装工程的交叉、配合中不可避免的停歇时间；②施工机械在场内单位工程之间变换位置及在施工过程中移动临时水电线路引起的临时停水、停电所发生的不可避免的间歇时间；③施工过程中水电维修用工；④隐蔽工程验收等工程质量检查影响的操作时间；⑤现场内单位工程之间操作地点转移影响的操作时间；⑥施工过程中工种之间交叉作业造成的不可避免的剔凿、修复、清理等用工；⑦施工过程中不可避免的直接少量零星用工。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]