[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51808":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},51808,53,1,"单选题","施工过程中，由于材料供应不及时所消耗的时间属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工本身造成的停工时间",true,{"key":16,"text":17,"correct":18},"B","非施工本身造成的停工时间",false,{"key":20,"text":21,"correct":18},"C","多余和偶然时间",{"key":23,"text":24,"correct":18},"D","不可避免的中断时间","停工时间是指在工作班内停止工作造成的工时损失。按其性质不同，停工时间可分为：①施工本身造成的停工时间，是由于施工组织不善、材料供应不及时、工作面准备工作不足、工作地点组织不良等情况引起的停工时间；②非施工本身造成的停工时间，是由于水源、电源中断等引起的停工。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]