[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51776":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51776,53,1,"单选题","关于施工技术交底的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工技术交底要求进行书面技术交底",false,{"key":16,"text":17,"correct":18},"B","施工技术交底是施工作业人员向施工单位负责人交底",true,{"key":20,"text":21,"correct":14},"C","技术交底书应由施工项目技术人员编制",{"key":23,"text":24,"correct":14},"D","每一分部工程开工前均应进行作业技术交底","开工前应由项目技术负责人向承担施工的负责人或分包单位进行书面技术交底，技术交底资料应办理签字手续并归档保存。每一分部工程开工前均应进行作业技术交底。技术交底书应由施工项目技术人员编制，并经项目技术负责人批准实施。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]