[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51775":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51775,53,1,"单选题","（ ）是施工阶段质量控制的重点。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","测量控制",false,{"key":16,"text":17,"correct":14},"B","计量控制",{"key":19,"text":20,"correct":14},"C","关键部位和关键工序质量控制",{"key":22,"text":23,"correct":24},"D","工序质量控制",true,"工序质量控制是施工阶段质量控制的重点。只有严格控制工序质量，才能确保施工项目实体质量。工序施工质量控制主要包括工序施工条件质量控制和工序施工效果质量控制。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]