[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51773":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},51773,53,1,"单选题","（ ）必须组织做好隐蔽工程的验收工作，参加地基基础、主体结构等分部工程的验收，参加单位工程和工程竣工验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工项目负责人",true,{"key":16,"text":17,"correct":18},"B","项目总监理工程师",false,{"key":20,"text":21,"correct":18},"C","建设单位项目负责人",{"key":23,"text":24,"correct":18},"D","勘察单位项目负责人","施工项目负责人必须组织做好隐蔽工程的验收工作，参加地基基础、主体结构等分部工程的验收，参加单位工程和工程竣工验收；必须在验收文件上签字，不得签署虚假文件。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]