[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51769,53,1,"单选题","关于建设单位质量责任的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位必须将工程发包给具有最高资质等级的单位",false,{"key":16,"text":17,"correct":18},"B","建设单位必须按合同约定采购建筑材料",true,{"key":20,"text":21,"correct":14},"C","建设单位可以将建设工程肢解发包",{"key":23,"text":24,"correct":14},"D","建设工程发包单位可以使承包方以低于成本的价格竞标","AC两项，建设单位应当将工程发包给具有相应资质等级的单位，建设单位不得将建设工程肢解发包；B项，按照合同约定，由建设单位采购建筑材料、建筑构配件和设备的，建设单位应当保证建筑材料、建筑构配件和设备符合设计文件和合同要求。D项，建设工程发包单位不得迫使承包方以低于成本的价格竞标，不得任意压缩合理工期。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]