[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51764":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51764,53,1,"单选题","（ ）应当自工程竣工验收合格之日起15日内，向工程所在地县级以上地方人民政府建设行政主管部门备案。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":18},"B","建设单位",true,{"key":20,"text":21,"correct":14},"C","监理单位",{"key":23,"text":24,"correct":14},"D","建设工程质量监督部门","工程建成后必须按国家有关规定进行竣工验收。建设工程经验收合格后，方可交付使用。建设单位应当自工程竣工验收合格之日起15日内，向工程所在地县级以上地方人民政府建设行政主管部门备案。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]