[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51757":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51757,53,1,"单选题","（ ）阶段是决定工程质量的关键环节。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","前期策划与决策",false,{"key":16,"text":17,"correct":18},"B","工程勘察设计",true,{"key":20,"text":21,"correct":14},"C","工程施工",{"key":23,"text":24,"correct":14},"D","工程竣工验收","工程平面布置和空间形式、结构和构造类型、使用材料、构配件、设备等的质量水平和功能要求，都是在工程设计阶段确定的，工程勘察设计阶段是决定工程质量的关键环节。A项，项目前期策划直接影响项目决策质量和设计质量。C项，工程施工是形成工程实体质量的决定性环节。D项，工程竣工验收对工程质量的作用是保证最终产品的总体质量。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]