[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51756":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51756,53,1,"单选题","当采用非代理型CM方式时，如果实际工程费用超过GMP，超出部分将由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分包商",false,{"key":16,"text":17,"correct":18},"B","CM单位",true,{"key":20,"text":21,"correct":14},"C","总承包商",{"key":23,"text":24,"correct":14},"D","设计单位","CM是指由建设单位委托一家CM单位承担项目管理工作，该CM单位以承包商身份进行施工管理，并在一定程度上影响工程设计活动。非代理型CM单位直接与分包单位签订分包合同，合同计价则采用保证最大工程费用（GMP）加酬金的方式。当采用非代理型CM方式时，CM单位将对工程费用的控制承担风险。如果实际工程费用超过GMP，超出部分将由CM单位承担；如果实际工程费用低于GMP，节约部分全部归建设单位所有。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]