[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51755":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},51755,53,1,"单选题","建设工程采用CM承包模式，由于采用分阶段发包，集中管理，实现了有条件的（ ），使设计与施工能够充分地搭接，有利于缩短建设工期。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","边设计，边施工",true,{"key":16,"text":17,"correct":18},"B","先设计，再施工",false,{"key":20,"text":21,"correct":18},"C","先设计，再审查",{"key":23,"text":24,"correct":18},"D","边设计，边审查","CM模式特别适用于实施周期长、工期要求紧迫的大型复杂工程。采用CM模式，由于采取分阶段发包，集中管理，实现了有条件的“边设计、边施工”，使工程设计与施工能够充分地搭接，有利于缩短建设工期。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]