[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51742,53,1,"单选题","在非代理型CM模式下，采用的合同计价形式为（ ）合同。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","保证最大工程费用",false,{"key":16,"text":17,"correct":18},"B","保证最大工程费用加酬金",true,{"key":20,"text":21,"correct":14},"C","固定总价",{"key":23,"text":24,"correct":14},"D","成本加酬金","非代理型CM单位直接与分包单位签订分包合同，合同计价则采用保证最大工程费用（GMP）加酬金的方式。这是因为CM合同总价是在CM合同签订之后，随着CM单位与各分包单位签约而逐步形成的。只有采用保证最大工程费用，建设单位才能控制工程总费用。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]