[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51741":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51741,53,1,"单选题","建设工程项目实施建筑工程管理（CM）模式时，代理型合同和非代理型合同的签订为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","均由建设单位与分包单位直接签订",false,{"key":16,"text":17,"correct":14},"B","均由CM单位与分包单位签订",{"key":19,"text":20,"correct":14},"C","代理型合同是CM单位和建设单位签订，非代理型合同是CM单位与分包单位签订",{"key":22,"text":23,"correct":24},"D","代理型合同是建设单位与分包单位签订，非代理型合同是CM单位与分包单位签订",true,"CM单位有代理型（Agency）和非代理型（Non-Agency）两种，因而使CM模式有两种实施方式：①代理型（Agency）CM方式：代理型CM单位不负责分包工程的发包，与分包单位的合同由建设单位直接签订，因而采用简单的成本加酬金合同形式。②非代理型（Non-Agency）CM模式：非代理型CM单位直接与分包单位签订分包合同，合同计价则采用保证最大工程费用（GMP）加酬金的方式。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]