[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51711":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51711,53,1,"单选题","工程施工合同中的发包人在合同履行中发生下列（ ）行为，属承包人违约。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","因发包人原因未能在计划开工日期前7天内下达开工通知的",false,{"key":16,"text":17,"correct":14},"B","因发包人原因未能按合同约定支付合同价款的",{"key":19,"text":20,"correct":21},"C","承包人在缺陷责任期及保修期内，未能在合理期限对工程缺陷进行修复",true,{"key":23,"text":24,"correct":14},"D","发包人提供的材料、工程设备的规格、数量或质量不符合合同约定","承包人在合同履行中发生下列情形之一的，属承包人违约：①承包人违反合同约定进行转包或违法分包的；②承包人违反合同约定采购和使用不合格的材料与工程设备的；③因承包人原因导致工程质量不符合合同要求的；④承包人违反合同约定，未经批准，擅自将已按照合同约定进入施工现场的材料或设备撤离施工现场的；⑤承包人未能按施工进度计划及时完成合同约定的工作，造成工期延误的；⑥承包人在缺陷责任期及保修期内，未能在合理期限对工程缺陷进行修复，或拒绝按发包人要求进行修复的；⑦承包人明确表示或者以其行为表明不履行合同主要义务的；⑧承包人未能按照合同约定履行其他义务的。ABD三项都属于发包人违约。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]