[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51697":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51697,53,1,"单选题","（ ）在签发工程暂停令时，可根据停工原因的影响范围和影响程度，确定停工范围。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目法人",false,{"key":16,"text":17,"correct":14},"B","项目经理",{"key":19,"text":20,"correct":14},"C","监理工程师",{"key":22,"text":23,"correct":24},"D","总监理工程师",true,"总监理工程师在签发工程暂停令时，可根据停工原因的影响范围和影响程度，确定停工范围。总监理工程师签发工程暂停令，应事先征得建设单位同意，在紧急情况下未能事先报告时，应在事后及时向建设单位作出书面报告。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]