[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51340":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},51340,53,1,"单选题","房地产开发项目管理中，工程量增减、索赔等事宜的处理，属于( )管理。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同",true,{"key":16,"text":17,"correct":18},"B","进度",false,{"key":20,"text":21,"correct":18},"C","费用",{"key":23,"text":24,"correct":18},"D","质量","房地产开发工程建设的进度、成本与质量管理的主要任务包括：组织管理、合同管理、进度管理、费用管理、质量管理。其中合同管理的工作是对施工前签订的施工合同进行管理，并处理工程量增减、合同纠纷、索赔等事宜。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]