[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51338":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51338,53,1,"单选题","下列各项不属于工程进度监理的主要任务的有( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","对项目建设周期进行具体的论证",false,{"key":16,"text":17,"correct":14},"B","编制项目总进度计划和阶段详细进度计划",{"key":19,"text":20,"correct":14},"C","监督阶段详细进度计划的执行",{"key":22,"text":23,"correct":24},"D","对取得的实际质量数据和施工单位履行质量职责的程度，与国家有关规定、技术标准进行比较，看其是否合乎要求",true,"工程进度监理，即监理单位受建设单位或业主委托，对工程进度情况所进行的监督管理活动，以保证施工工程按照合同中预定方案和支付时间完成，其主要任务是对项目建设周期进行具体的论证，编制项目总进度计划和阶段详细进度计划，监督阶段详细进度计划的执行，对施工现场进行调研和分析。选项D属于工程质量监理的内容。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]