[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51334":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},51334,53,1,"单选题","工程进度管理中的客观进度计划常用的表示方法是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","横道图法和网络图法",true,{"key":16,"text":17,"correct":18},"B","单项工程",false,{"key":20,"text":21,"correct":18},"C","单位工程",{"key":23,"text":24,"correct":18},"D","全部工程","客观进度计划。即从工程项目开始准备到竣工验收的各阶段进度计划，常用横道图法和网络图法表示。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]