[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51333":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51333,53,1,"单选题","下列选项中，不属于按照工程项目建设阶段划分的进度计划的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","客观进度计划",false,{"key":16,"text":17,"correct":14},"B","总进度计划",{"key":19,"text":20,"correct":21},"C","企业工程进度计划",true,{"key":23,"text":24,"correct":14},"D","单位工程进度计划","按照工程项目建设阶段划分，进度计划一般分为：①客观进度计划，即从工程项目开始准备到竣工验收的各阶段进度计划；②总进度计划，由承包单位的技术部门、计划部门、质量监督部门等在项目负责人的领导和监理工程师的主持下编制；③单位工程进度计划，以单位工程为对象进行编制。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]