[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51324":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51324,53,1,"单选题","施工现场“三通一平”中的“三通”是指( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","通给水、排水和道路",false,{"key":16,"text":17,"correct":18},"B","通给水、电力和道路",true,{"key":20,"text":21,"correct":14},"C","通给水、电信和电力",{"key":23,"text":24,"correct":14},"D","通电力、燃气和道路","施工现场的临时“三通一平”是为正式进行建筑施工做准备，其中“三通”包括：与供水、供电部门联系，铺设施工中临时用水、用电管线，修筑施工用的临时道路。“一平”是指由建筑单位进行场地清理并按竖向规划设计平整场地，修建施工现场的防护围墙和临时用房。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]