[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51323":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51323,53,1,"单选题","房地产开发企业申请领取施工许可证时，建设工期不足一年的，到位资金原则上不得少于工程合同价的______，工期超过一年的，到位资金原则上不得少于工程合同价的______。（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30%；50%",false,{"key":16,"text":17,"correct":14},"B","30%；60%",{"key":19,"text":20,"correct":21},"C","50%；30%",true,{"key":23,"text":24,"correct":14},"D","60%，30%","房地产开发企业申请领取施工许可证的，建设工期不足一年，到位资金原则上不得少于工程合同价的50%，建设工期超过一年，到位资金原则上不得少于工程合同价的30%。建设单位应当提供银行出具的到位资金证明，有条件的可以实行银行付款保函或者其他第三方担保。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]