[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51312":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51312,53,1,"单选题","下列各项中，制定施工方案不包括( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工组织与协调计划",false,{"key":16,"text":17,"correct":14},"B","建材与设备供应计划",{"key":19,"text":20,"correct":21},"C","工程质量控制计划",true,{"key":23,"text":24,"correct":14},"D","基础设施配套的接洽与协商计划","建设施工方案主要包括：施工组织与协调计划，建材与设备供应计划，施工图设计方案，基础设施配套的接洽与协商计划，编制工程量清单和工程时间进度表以及现金流量表，与承包商谈判以及签约计划等。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]