[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51026":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51026,53,1,"单选题","项目成本降低额是考核项目成本目标的依据，其内容是指( )的差额。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","预算成本与目标成本",false,{"key":16,"text":17,"correct":14},"B","计划成本与目标成本",{"key":19,"text":20,"correct":14},"C","预算成本与实际成本",{"key":22,"text":23,"correct":24},"D","计划成本与实际成本",true,"计划成本与实际成本的差额，称为项目成本降低额，项目成本降低额与计划成本的比率，称为项目成本降低率，都是考核项目成本目标的依据。@##",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]