[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51022":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51022,53,1,"单选题","工程成本管理的目的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","采取措施降低工程实际成本",false,{"key":16,"text":17,"correct":14},"B","组织工程成本核算和分析",{"key":19,"text":20,"correct":21},"C","将实际成本控制在计划成本之内",true,{"key":23,"text":24,"correct":14},"D","强化对工程成本责任的检查和考核","工程成本管理的目的是将实际成本控制在计划成本之内 。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]