[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51019":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},51019,53,1,"单选题","从主观原因分析，造成工程项目成本失控的关键是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本责任不到位. 管理混乱",true,{"key":16,"text":17,"correct":18},"B","成本核算失真. 滞后",false,{"key":20,"text":21,"correct":18},"C","计划成本编制不科学. 不及时",{"key":23,"text":24,"correct":18},"D","成本分析走过场. 没抓住主要原因","影响工程成本的因素很多，而且也错综复杂，但从主观原因分析，工程成本失控，往往是成本责任不到位、责任不清、制度不健全、管理混乱造成的。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]