[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51016":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},51016,53,1,"单选题","装饰工程因用工数变动影响而造成人工费超支额为( )元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15 000",true,{"key":16,"text":17,"correct":18},"B","16 000",false,{"key":20,"text":21,"correct":18},"C","17 000",{"key":23,"text":24,"correct":18},"D","18 000","50*（10300-10000）=15000",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]