[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51014":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51014,53,1,"单选题","已知某竣工建筑工程项目人工费成本资料如下： (1)主体工程：结算人工费日单价为40元，总用工数为lO 000工日，实际人工费日单价为45元，总用工数为15 000工日； (2)装饰工程：结算人工费日单价为50元，总用工数为10 000工日，实际人工费日单价为70元，总用工数为10 300工日。 根据以上资料，回答63-66题： 主体工程因用工数变动影响而造成人工费超支额为( )元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","100 000",false,{"key":16,"text":17,"correct":14},"B","159 000",{"key":19,"text":20,"correct":14},"C","180 000",{"key":22,"text":23,"correct":24},"D","200 000",true,"40*（15000-10000）=200000",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]