[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51008":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51008,53,1,"单选题","某施工企业在进行工程成本分析时发现机械使用费超支，若想进一步分析超支的具体原因，应采用的分析方法是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","对比分析法",false,{"key":16,"text":17,"correct":14},"B","平衡分析法",{"key":19,"text":20,"correct":21},"C","因素分析法",true,{"key":23,"text":24,"correct":14},"D","盈亏平衡法","因素分析法也称连环替代法。运用因素分析法分析问题时必须按一定的顺序，首先确定差异的总额和方向，其次分析差异的构成和各因素的关系，从量差和价差上测定因素变动对差异的影响程度和方向。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]