[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50979":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50979,53,1,"单选题","施工企业成本包括( )两个部分。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","资本化成本和费用化成本",false,{"key":16,"text":17,"correct":14},"B","直接工程成本和措施成本",{"key":19,"text":20,"correct":21},"C","工程成本和期间成本",true,{"key":23,"text":24,"correct":14},"D","变动成本和间接成本","施工企业成本包括工程成本和期间成本两个部分，工程成本是企业成本的基础和核心，是施工企业的主要产品成本，亦称施工项目成本，是指企业以施工项目作为成本核算对象的施工过程中所耗费的生产资料转移的价值和劳动者所创造的价值的货币形式。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]