[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50954":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},50954,53,1,"单选题","采用工程量清单方式招标，招标工程量清单必须作为招标文件的组成部分，其准确性、完整性由( )负责。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标人",true,{"key":16,"text":17,"correct":18},"B","投标人",false,{"key":20,"text":21,"correct":18},"C","招标机构",{"key":23,"text":24,"correct":18},"D","投标单位","采用工程量清单方式招标，招标工程量清单必须作为招标文件的组成部分，其准确性、完整性由招标人负责。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]