[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50953":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50953,53,1,"单选题","在工程量清单计价模式下，下列各项因不可抗力导致的损失或费用中，应由承包人承担的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程本身损害导致的损失",false,{"key":16,"text":17,"correct":14},"B","工程所需清理费用",{"key":19,"text":20,"correct":21},"C","承包人机械设备损坏的损失",true,{"key":23,"text":24,"correct":14},"D","因工程损害导致第三方人员伤亡的相应费用","由于承包人使用机械设备、施工技术以及组织管理水平等自身原因造成施工费用增加的，由承包人全部负担。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]