[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50941":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},50941,53,1,"单选题","劳动定额的工人工作时间中，为保证基本工作能顺利完成所消耗的时间，称为工人的( )工作时间。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基本",false,{"key":16,"text":17,"correct":18},"B","辅助",true,{"key":20,"text":21,"correct":14},"C","准备",{"key":23,"text":24,"correct":14},"D","有效","有效工作时间包括：基本工作时间就、辅助工作时间、准备与结束工作时间。主要是考察不同工作时间的概念以及区分。@##",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]