[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50910":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},50910,53,1,"单选题","编制机械台班消耗定额时，汽车装货和卸货时停车消耗的机械工作时间属于( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不可避免中断时间",true,{"key":16,"text":17,"correct":18},"B","有效工作时间",false,{"key":20,"text":21,"correct":18},"C","不可避免的无负荷工作时间",{"key":23,"text":24,"correct":18},"D","多余工作时间","不可避免的中断时间是指由于施工工艺特点引起的工作中断所必须的时间。汽车装货和卸货时停车消耗的机械工作时间属于不可避免的工作中断时间。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]