[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50889":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},50889,53,1,"单选题","每米管道工程的定额人工消耗量为( )工日。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","4．29",false,{"key":16,"text":17,"correct":14},"B","4．59",{"key":19,"text":20,"correct":14},"C","4．95",{"key":22,"text":23,"correct":24},"D","5．19",true,"（4+0.72）*1.1=5.19",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]