[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50886":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50886,53,1,"单选题","每米管道保温的产量定额为( )工日。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1．19",false,{"key":16,"text":17,"correct":14},"B","1．29",{"key":19,"text":20,"correct":21},"C","1．39",true,{"key":23,"text":24,"correct":14},"D","1．49","产量定额，就是在合理的劳动组织和合理使用材料的条件下，某种专业、某种技术等级的工人班组或个人在单位工日中所应完成的合格产品的数量。产量定额与时间定额互为倒数。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]