[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50884":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},50884,53,1,"单选题","某热力管道工程，完成每米管道保温所需要的工作延续时间为5.77小时，除保温层作业外，每米管道工程安装、防腐、包装箱等作业的人工时间定额为4个工日。各项作业人工幅度差为10％。回答69-71题: 每米管道保温的人工时间定额为( )工日。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","O．62",false,{"key":16,"text":17,"correct":18},"B","O．72",true,{"key":20,"text":21,"correct":14},"C","O．82",{"key":23,"text":24,"correct":14},"D","O．92","5.77\u002F8=0.72工日",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]